Whole-project rollup at the latest vintage per category: printed project-level rows are preferred, and mining areas are summed (tonnes-weighted grade) only where the issuer prints no project-level row. Per-area and per-source detail in the Current R&R table below.
| Category | Tonnes (Mt) | Grade (g/t Au) | Contained (Moz Au) | As at |
|---|---|---|---|---|
| Measured | 2.70 Mt | 0.66 g/t | 0.06 Moz | 31 Dec 2025 |
| Indicated | 182.00 Mt | 0.67 g/t | 3.90 Moz | 31 Mar 2026 |
| Inferred | 233.00 Mt | 0.53 g/t | 3.90 Moz | 31 Mar 2026 |
| Total Resources | 275.80 Mt | 0.65 g/t | 5.80 Moz | 31 Mar 2026 |
| Proved | 1.90 Mt | 0.69 g/t | 0.04 Moz | 31 Mar 2026 |
| Probable | 116.80 Mt | 0.46 g/t | 1.73 Moz | 31 Mar 2026 |
| Total Reserves | 118.70 Mt | 0.46 g/t | 1.80 Moz | 31 Mar 2026 |
Sub-category rows are as disclosed (no Reserves-treatment netting); the Total rows honour the Resources treatment and Inferred-policy toggles, so components may not sum to the Total.
Dotted tonnes/grade are derived under the active Resources treatment: tonnes are netted of (or grossed by) the reserve tonnage alongside contained, and grade is re-derived as netted contained ÷ netted tonnes — not the published figures.
| Category | Tonnes (Mt) | Grade (% Cu) | Contained (Mt Cu) | As at |
|---|---|---|---|---|
| Measured | 2.70 Mt | 0.11% | 2.97 kt Cu | 31 Dec 2025 |
| Indicated | 182.00 Mt | 0.12% | 0.22 Mt Cu | 31 Mar 2026 |
| Inferred | 233.00 Mt | 0.06% | 0.14 Mt Cu | 31 Mar 2026 |
| Total Resources | 300.20 Mt | 0.10% | 0.29 Mt Cu | 31 Mar 2026 |
| Proved |
Percentile of this project's current total Resource among covered peers (P100 = largest / highest grade). Basis and Inferred toggles apply.
| Area | Category | Tonnes (Mt) | Au | Cu | As at | Source | Provenance | ||
|---|---|---|---|---|---|---|---|---|---|
| Grade (g/t Au) | Contained (Moz Au) | Grade (% Cu) | Contained (Mt Cu) | ||||||
| Total | Measured | 2.70 Mt | 0.66 g/t | 0.06 Moz | 0.11% | 2.97 kt Cu | 31 Dec 2025 | 17Unverified | |
| 0.13% |
| 2.47 kt Cu |
| 31 Mar 2026 |
| Probable | 116.80 Mt | 0.06% | 0.07 Mt Cu | 31 Mar 2026 |
| Total Reserves | 118.70 Mt | 0.06% | 0.07 Mt Cu | 31 Mar 2026 |
Sub-category rows are as disclosed (no Reserves-treatment netting); the Total rows honour the Resources treatment and Inferred-policy toggles, so components may not sum to the Total.
Dotted tonnes/grade are derived under the active Resources treatment: tonnes are netted of (or grossed by) the reserve tonnage alongside contained, and grade is re-derived as netted contained ÷ netted tonnes — not the published figures.
notes (3)Ref: 17
|
| Total | Indicated | 182.00 Mt | 0.67 g/t | 3.90 Moz | 0.12% | 0.22 Mt Cu | 31 Mar 2026 | 17Unverified | notes (4)Ref: 17
QA notes:
|
| Total | Inferred | 233.00 Mt | 0.53 g/t | 3.90 Moz | 0.06% | 0.14 Mt Cu | 31 Mar 2026 | 17Unverified | notes (4)Ref: 17
QA notes:
|
| Total | Total Resources | 275.80–300.20 Mt | 0.65 g/t | 5.80 Moz | 0.10% | 0.29 Mt Cu | 31 Mar 2026 | 17Unverified | notes (4)Ref: 17
QA notes:
|
| Main Dome Underground | Indicated | 7.80 Mt | 2.28 g/t | 0.60 Moz | 0.45% | 0.04 Mt Cu | 31 Dec 2025 | 17Unverified | notes (4)Ref: 17
QA notes:
|
| Main Dome Underground | Inferred | 4.40 Mt | 1.90 g/t | 0.30 Moz | 0.33% | 0.01 Mt Cu | 31 Dec 2025 | 17Unverified | notes (4)Ref: 17
QA notes:
|
| Main Dome Underground | Total Resources | 12.00 Mt † | 2.14 g/t † | 0.00 Moz | — | — | 31 Dec 2025 | 17Unverified | notes (4)Ref: 17
QA notes:
|
| Stockpiles | Measured | 2.70 Mt | 0.66 g/t | 0.06 Moz | 0.11% | 2.97 kt Cu | 31 Dec 2025 | 17Unverified | notes (3)Ref: 17
|
| Stockpiles | Indicated | 21.00 Mt | 0.33 g/t | 0.20 Moz | 0.04% | 0.01 Mt Cu | 31 Dec 2025 | 17Unverified | notes (3)Ref: 17
|
| Stockpiles | Total Resources | 24.00 Mt † | 0.37 g/t † | 0.00 Moz | — | — | 31 Dec 2025 | 17Unverified | notes (4)Ref: 17
QA notes:
|
| VSC | Indicated | 33.00 Mt | 1.11 g/t | 1.20 Moz | 0.32% | 0.11 Mt Cu | 31 Dec 2025 | 17Unverified | notes (4)Ref: 17
QA notes:
|
| VSC | Inferred | 4.20 Mt | 0.97 g/t | 0.10 Moz | 0.40% | 0.02 Mt Cu | 31 Dec 2025 | 17Unverified | notes (4)Ref: 17
QA notes:
|
| VSC | Total Resources | 37.00 Mt † | 1.09 g/t † | 0.00 Moz | — | — | 31 Dec 2025 | 17Unverified | notes (3)Ref: 17
|
| West Dome Open Pit | Indicated | 117.00 Mt | 0.46 g/t | 1.70 Moz | 0.05% | 0.06 Mt Cu | 31 Mar 2026 | 17Unverified | notes (4)Ref: 17
QA notes:
|
| West Dome Open Pit | Inferred | 219.00 Mt | 0.45 g/t | 3.20 Moz | 0.04% | 0.09 Mt Cu | 31 Mar 2026 | 17Unverified | notes (3)Ref: 17
|
| West Dome Open Pit | Total Resources | 194.80 Mt | 0.45 g/t | 2.80 Moz | — | — | 31 Mar 2026 | 17Unverified | notes (3)Ref: 17
|
| West Dome Open Pit - High Grade | Indicated | 79.00 Mt | 0.52 g/t | 1.30 Moz | 0.05% | 0.04 Mt Cu | 31 Dec 2025 | 5Unverified | notes (4)Ref: 5
QA notes:
|
| West Dome Open Pit - High Grade | Inferred | 179.00 Mt | 0.53 g/t | 3.00 Moz | 0.05% | 0.09 Mt Cu | 31 Dec 2025 | 5Unverified | notes (4)Ref: 5
QA notes:
|
| West Dome Open Pit - High Grade | Total Resources | 258.00 Mt | 0.53 g/t | 4.40 Moz | — | — | 31 Dec 2025 | 5Unverified | notes (3)Ref: 5
|
| West Dome Open Pit - Low Grade | Indicated | 23.00 Mt | 0.23 g/t | 0.20 Moz | 0.04% | 0.01 Mt Cu | 31 Dec 2025 | 5Unverified | notes (4)Ref: 5
QA notes:
|
| West Dome Open Pit - Low Grade | Inferred | 57.00 Mt | 0.22 g/t | 0.40 Moz | 0.02% | 0.01 Mt Cu | 31 Dec 2025 | 5Unverified | notes (3)Ref: 5
|
| West Dome Open Pit - Low Grade | Total Resources | 80.00 Mt | 0.22 g/t | 0.60 Moz | — | — | 31 Dec 2025 | 5Unverified | notes (4)Ref: 5
QA notes:
|
| West Dome Underground - Lower Limey Unit (LLU) | Indicated | 1.60 Mt | 2.99 g/t | 0.20 Moz | 0.49% | 0.01 Mt Cu | 31 Dec 2025 | 9Unverified | notes (3)Ref: 9
|
| West Dome Underground - Lower Limey Unit (LLU) | Inferred | 1.90 Mt | 3.67 g/t | 0.20 Moz | 0.53% | 0.01 Mt Cu | 31 Dec 2025 | 9Unverified | notes (3)Ref: 9
|
| West Dome Underground - Lower Limey Unit (LLU) | Total Resources | 3.50 Mt | 3.36 g/t | 0.40 Moz | — | — | 31 Dec 2025 | 9Unverified | notes (4)Ref: 9
QA notes:
|
| West Dome Underground - Western Stockwork Corridor (WSC) | Indicated | 1.30 Mt | 1.43 g/t | 0.10 Moz | 0.48% | 0.01 Mt Cu | 31 Dec 2025 | 9Unverified | notes (3)Ref: 9
|
| West Dome Underground - Western Stockwork Corridor (WSC) | Inferred | 3.20 Mt | 1.48 g/t | 0.20 Moz | 0.35% | 0.01 Mt Cu | 31 Dec 2025 | 9Unverified | notes (3)Ref: 9
|
| West Dome Underground - Western Stockwork Corridor (WSC) | Total Resources | 4.50 Mt | 1.47 g/t | 0.20 Moz | — | — | 31 Dec 2025 | 9Unverified | notes (4)Ref: 9
QA notes:
|
| Area | Category | Tonnes (Mt) | Au | Cu | As at | Source | Provenance | ||
|---|---|---|---|---|---|---|---|---|---|
| Grade (g/t Au) | Contained (Moz Au) | Grade (% Cu) | Contained (Mt Cu) | ||||||
| Total | Proved | 1.90 Mt | 0.69 g/t | 0.04 Moz | 0.13% | 2.47 kt Cu | 31 Mar 2026 | 5Unverified | notes (2)Ref: 5
|
| Total | Probable | 116.80 Mt | 0.46 g/t | 1.73 Moz | 0.06% | 0.07 Mt Cu | 31 Mar 2026 | 5Unverified | notes (2) |
| Total | Total Reserves | 118.70 Mt | 0.46 g/t | 1.80 Moz | 0.06% | 0.07 Mt Cu | 31 Mar 2026 | 5Unverified | notes (3) |
| Dump Leach | Probable | 2.00 Mt | 0.19 g/t | 0.01 Moz | — | — | 31 Mar 2026 | 5Unverified | notes (3) |
| Low Grade Stockpiles | Probable | 20.30 Mt | 0.33 g/t | 0.20 Moz | 0.04% | 0.01 Mt Cu | 31 Dec 2024 | 43Unverified | notes (5) |
| Main Dome Underground | Probable | 3.60 Mt | 1.33 g/t | 0.20 Moz | 0.31% | 0.01 Mt Cu | 31 Mar 2026 | 5Unverified | notes (4) |
| ROM Stockpiles | Proved | 9.60 Mt | 0.68 g/t | 0.20 Moz | 0.07% | 0.01 Mt Cu | 31 Dec 2024 | 43Unverified | notes (5) |
| Stockpiles | Proved | 1.90 Mt | 0.69 g/t | 0.04 Moz | 0.13% | 2.47 kt Cu | 31 Mar 2026 | 5Unverified | notes (3) |
| Stockpiles | Probable | 20.60 Mt | 0.33 g/t | 0.22 Moz | 0.04% | 0.01 Mt Cu | 31 Mar 2026 | 5Unverified | notes (3) |
| Stockpiles | Total Reserves | 22.50 Mt | 0.36 g/t | 0.30 Moz | 0.05% | 0.01 Mt Cu | 31 Mar 2026 | 5Unverified | notes (4) |
| West Dome Open Pit | Probable | 90.60 Mt | 0.46 g/t | 1.40 Moz | 0.05% | 0.05 Mt Cu | 31 Mar 2026 | 5Unverified | notes (3)Ref: 5 |
Rows are hierarchical, not additive — do not sum a column across rows. Whole-project rows (Area “Total”) already contain the indented named-area rows beneath them, and an issuer's printed per-deposit total can itself contain other listed areas. All derived totals and rollups on this site already exclude the overlapping rows.
Dotted Total-row tonnes/grade are derived under the active Resources treatment: tonnes netted of (or grossed by) the reserve tonnage alongside contained, grade re-derived as netted contained ÷ netted tonnes — not the published figures.
† Total-row tonnes/grade as published (not net): the reserve statement prints no tonnage to net out, so only the contained figure honours the Resources treatment there.