Whole-project rollup at the latest vintage per category: printed project-level rows are preferred, and mining areas are summed (tonnes-weighted grade) only where the issuer prints no project-level row. Per-area and per-source detail in the Current R&R table below.
| Category | Tonnes (Mt) | Grade (g/t Au) | Contained (Moz Au) | As at |
|---|---|---|---|---|
| Measured | — | — | — | — |
| Indicated | 36.20 Mt | 0.35 g/t | 0.41 Moz | 24 Nov 2025 |
| Inferred | 7.70 Mt | 0.37 g/t | 0.09 Moz | 24 Nov 2025 |
| Total Resources | 43.90 Mt | 0.35 g/t | 0.51 Moz | 24 Nov 2025 |
| Proved | — | — | — | — |
| Probable | — | — | — | — |
| Total Reserves | — | — | — | — |
Percentile of this project's current total Resource among covered peers (P100 = largest / highest grade). Basis and Inferred toggles apply.
| Area | Category | Tonnes (Mt) | Au | As at | Source | Provenance | |
|---|---|---|---|---|---|---|---|
| Grade (g/t Au) | Contained (Moz Au) | ||||||
| Total | Indicated | 36.20 Mt | 0.35 g/t | 0.41 Moz | 24 Nov 2025 | Table 1: Hollinger MRE Summary — Total row, IndicatedUnverified | |
notes (3)Source: STLLR Gold's Hollinger Tailings Project Maiden Mineral Resource Estimate Provides A Strong Foundation for Exploring Future Short-Term Development Under Ontario's New Recovery of Minerals Regime · published 25 Nov 2025 Ref: Table 1: Hollinger MRE Summary — Total row, Indicated
QA notes:
|
| Total | Inferred | 7.70 Mt | 0.37 g/t | 0.09 Moz | 24 Nov 2025 | Table 1: Hollinger MRE Summary — Total row, InferredUnverified | notes (3)Source: STLLR Gold's Hollinger Tailings Project Maiden Mineral Resource Estimate Provides A Strong Foundation for Exploring Future Short-Term Development Under Ontario's New Recovery of Minerals Regime · published 25 Nov 2025 Ref: Table 1: Hollinger MRE Summary — Total row, Inferred
QA notes:
|
| Total | Total Resources | 43.90 Mt | 0.35 g/t | 0.51 Moz | 24 Nov 2025 | derived from 2 rows | — |
| Phase 1 | Indicated | 16.10 Mt | 0.41 g/t | 0.21 Moz | 24 Nov 2025 | Table 1: Hollinger MRE SummaryUnverified | notes (2)Source: STLLR Gold's Hollinger Tailings Project Maiden Mineral Resource Estimate Provides A Strong Foundation for Exploring Future Short-Term Development Under Ontario's New Recovery of Minerals Regime · published 25 Nov 2025 Ref: Table 1: Hollinger MRE Summary
|
| Phase 1 | Inferred | 4.10 Mt | 0.43 g/t | 0.06 Moz | 24 Nov 2025 | Table 1: Hollinger MRE SummaryUnverified | notes (3)Source: STLLR Gold's Hollinger Tailings Project Maiden Mineral Resource Estimate Provides A Strong Foundation for Exploring Future Short-Term Development Under Ontario's New Recovery of Minerals Regime · published 25 Nov 2025 Ref: Table 1: Hollinger MRE Summary
QA notes:
|
| Phase 2 | Indicated | 20.20 Mt | 0.31 g/t | 0.20 Moz | 24 Nov 2025 | Table 1: Hollinger MRE SummaryUnverified | notes (2)Source: STLLR Gold's Hollinger Tailings Project Maiden Mineral Resource Estimate Provides A Strong Foundation for Exploring Future Short-Term Development Under Ontario's New Recovery of Minerals Regime · published 25 Nov 2025 Ref: Table 1: Hollinger MRE Summary
|
| Phase 2 | Inferred | 3.60 Mt | 0.31 g/t | 0.04 Moz | 24 Nov 2025 | Table 1: Hollinger MRE SummaryUnverified | notes (3)Source: STLLR Gold's Hollinger Tailings Project Maiden Mineral Resource Estimate Provides A Strong Foundation for Exploring Future Short-Term Development Under Ontario's New Recovery of Minerals Regime · published 25 Nov 2025 Ref: Table 1: Hollinger MRE Summary
QA notes:
|
Rows are hierarchical, not additive — do not sum a column across rows. Whole-project rows (Area “Total”) already contain the indented named-area rows beneath them, and an issuer's printed per-deposit total can itself contain other listed areas. All derived totals and rollups on this site already exclude the overlapping rows.