These choices persist and are added to shared URLs.
Whole-project rollup at the latest vintage per category: printed project-level rows are preferred, and mining areas are summed (tonnes-weighted grade) only where the issuer prints no project-level row. Per-area and per-source detail in the Current R&R table below.
| Category | Tonnes (Mt) | Grade (g/t Au) | Contained (Moz Au) | As at |
|---|---|---|---|---|
| Measured | — | — | — | — |
| Indicated | 2.86 Mt | 0.39 g/t | 0.04 Moz | 31 Dec 2024 |
| Inferred | 1.64 Mt | 0.39 g/t | 0.02 Moz | 31 Dec 2024 |
| Total Resources | 4.50 Mt | 0.39 g/t | 0.06 Moz | 31 Dec 2024 |
| Proved | — | — | — | — |
| Probable | — | — | — | — |
| Total Reserves | — | — | — | — |
| Category | Tonnes (Mt) | Grade (g/t Ag) | Contained (Moz Ag) | As at |
|---|---|---|---|---|
| Measured | — | — | — | — |
| Indicated | 2.86 Mt | 13.30 g/t | 1.23 Moz | 31 Dec 2024 |
| Inferred | 1.64 Mt | 12.10 g/t | 0.64 Moz | 31 Dec 2024 |
| Total Resources | 4.50 Mt | 12.86 g/t | 1.86 Moz | 31 Dec 2024 |
| Proved | — | — | — | — |
| Probable |
| Category | Tonnes (Mt) | Grade (% Cu) | Contained (Mt Cu) | As at |
|---|---|---|---|---|
| Measured | — | — | — | — |
| Indicated | 2.86 Mt | 1.58% | 0.05 Mt Cu | 31 Dec 2024 |
| Inferred | 1.64 Mt | 1.43% | 0.02 Mt Cu | 31 Dec 2024 |
| Total Resources | 4.50 Mt | 1.52% | 0.07 Mt Cu | 31 Dec 2024 |
| Proved | — | — | — | — |
| Probable |
Percentile of this project's current total Resource among covered peers (P100 = largest / highest grade). Basis and Inferred toggles apply.
| Area | Category | Tonnes (Mt) | Au | Ag | Cu | As at | Source | Provenance | |||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Grade (g/t Au) | Contained (Moz Au) | Grade (g/t Ag) | Contained (Moz Ag) | Grade (% Cu) | Contained (Mt Cu) | ||||||
| Total | Indicated | 2.86 Mt | 0.39 g/t | 0.04 Moz | 13.30 g/t | 1.23 Moz | 1.58% | ||||
| — |
| — |
| — |
| Total Reserves | — | — | — | — |
| — |
| — |
| — |
| Total Reserves | — | — | — | — |
| 31 Dec 2024 |
| Table 1: Summary of Bull River Underground Mineral Resource - Effective Date December 31, 2024Unverified |
notes (5)Source: Canadian Critical Minerals Announces Increases of Indicated Metal of 11% for Copper and 17% for Gold at the Bull River Mine · published 04 Mar 2025 Ref: Table 1: Summary of Bull River Underground Mineral Resource - Effective Date December 31, 2024
QA notes:
|
| Total | Total Resources | 4.50 Mt | 0.39 g/t | 0.06 Moz | 12.86 g/t | 1.86 Moz | 1.52% | 0.07 Mt Cu | 31 Dec 2024 | derived from 2 rows | — |
| Underground | Inferred | 1.64 Mt | 0.39 g/t | 0.02 Moz | 12.10 g/t | 0.64 Moz | 1.43% | 0.02 Mt Cu | 31 Dec 2024 | Table 1: Summary of Bull River Underground Mineral Resource - Effective Date December 31, 2024Unverified | notes (3)Source: Canadian Critical Minerals Announces Increases of Indicated Metal of 11% for Copper and 17% for Gold at the Bull River Mine · published 04 Mar 2025 Ref: Table 1: Summary of Bull River Underground Mineral Resource - Effective Date December 31, 2024
|
Rows are hierarchical, not additive — do not sum a column across rows. Whole-project rows (Area “Total”) already contain the indented named-area rows beneath them, and an issuer's printed per-deposit total can itself contain other listed areas. All derived totals and rollups on this site already exclude the overlapping rows.