These choices persist and are added to shared URLs.
Whole-project rollup at the latest vintage per category: printed project-level rows are preferred, and mining areas are summed (tonnes-weighted grade) only where the issuer prints no project-level row. Per-area and per-source detail in the Current R&R table below.
| Category | Tonnes (Mt) | Grade (g/t Au) | Contained (Moz Au) | As at |
|---|---|---|---|---|
| Measured | — | — | — | — |
| Indicated | 32.34 Mt | 0.05 g/t | 0.05 Moz | 31 Dec 2023 |
| Inferred | 0.20 Mt | 0.11 g/t | 0.72 koz | 31 Dec 2023 |
| Total Resources | 32.54 Mt | 0.05 g/t | 0.05 Moz | 31 Dec 2023 |
| Proved | — | — | — | — |
| Probable | — | — | — | — |
| Total Reserves | — | — | — | — |
| Category | Tonnes (Mt) | Grade (% Cu) | Contained (Mt Cu) | As at |
|---|---|---|---|---|
| Measured | — | — | — | — |
| Indicated | 47.06 Mt | 0.31% | 0.15 Mt Cu | 31 Dec 2023 |
| Inferred | 0.22 Mt | 0.89% | 1.96 kt Cu | 31 Dec 2023 |
| Total Resources | 47.28 Mt | 0.32% | 0.15 Mt Cu | 31 Dec 2023 |
| Proved | — | — | — | — |
| Probable |
| Category | Tonnes (Mt) | Grade (% Ni) | Contained (Mt Ni) | As at |
|---|---|---|---|---|
| Measured | — | — | — | — |
| Indicated | 47.06 Mt | 0.27% | 0.13 Mt Ni | 31 Dec 2023 |
| Inferred | 0.22 Mt | 0.31% | 0.69 kt Ni | 31 Dec 2023 |
| Total Resources | 47.28 Mt | 0.27% | 0.13 Mt Ni | 31 Dec 2023 |
| Proved | — | — | — | — |
| Probable |
| Category | Tonnes (Mt) | Grade (% Co) | Contained (Mt Co) | As at |
|---|---|---|---|---|
| Measured | — | — | — | — |
| Indicated | 47.06 Mt | 0.01% | 0.01 Mt Co | 31 Dec 2023 |
| Inferred | 0.22 Mt | 0.02% | 0.04 kt Co | 31 Dec 2023 |
| Total Resources | 47.28 Mt | 0.01% | 0.01 Mt Co | 31 Dec 2023 |
| Proved | — | — | — | — |
| Probable |
Percentile of this project's current total Resource among covered peers (P100 = largest / highest grade). Basis and Inferred toggles apply.
| Area | Category | Tonnes (Mt) | Au | Cu | Ni | Co | As at | Source | Provenance | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Grade (g/t Au) | Contained (Moz Au) | Grade (% Cu) | Contained (Mt Cu) | Grade (% Ni) | Contained (Mt Ni) | Grade (% Co) | Contained (Mt Co) | ||||||
| Total | Total Resources | 32.54–47.28 Mt | |||||||||||
| — |
| — |
| — |
| Total Reserves | — | — | — | — |
| — |
| — |
| — |
| Total Reserves | — | — | — | — |
| — |
| — |
| — |
| Total Reserves | — | — | — | — |
| 0.05 g/t | 0.05 Moz |
| 0.32% | 0.15 Mt Cu |
| 0.27% | 0.13 Mt Ni |
| 0.01% | 0.01 Mt Co |
| 31 Dec 2023 |
| — |
| Makwa Open Pit HG1 | Indicated | 4.85 Mt | — | — | 0.17% | 0.01 Mt Cu | 0.89% | 0.04 Mt Ni | 0.03% | 1.45 kt Co | 31 Dec 2023 | Table 1B. Makwa Pit Constrained and Underground Resources as of December 31, 2023Unverified | notes (4)Source: Grid Metals Corp. Files National Instrument 43-101 Technical Report for MM Copper/Nickel Project in Southeastern Manitoba · published 24 June 2024 Ref: Table 1B. Makwa Pit Constrained and Underground Resources as of December 31, 2023
QA notes:
|
| Makwa Open Pit LG1 | Indicated | 9.37 Mt | — | — | 0.08% | 0.01 Mt Cu | 0.28% | 0.03 Mt Ni | 0.01% | 0.94 kt Co | 31 Dec 2023 | Table 1B. Makwa Pit Constrained and Underground Resources as of December 31, 2023Unverified | notes (4)Source: Grid Metals Corp. Files National Instrument 43-101 Technical Report for MM Copper/Nickel Project in Southeastern Manitoba · published 24 June 2024 Ref: Table 1B. Makwa Pit Constrained and Underground Resources as of December 31, 2023
QA notes:
|
| Makwa Open Pit LG1 | Inferred | 0.02 Mt | — | — | 0.04% | <0.01 kt Cu | 0.23% | 0.04 kt Ni | 0.01% | <0.01 kt Co | 31 Dec 2023 | Table 1B. Makwa Pit Constrained and Underground Resources as of December 31, 2023Unverified | notes (4)Source: Grid Metals Corp. Files National Instrument 43-101 Technical Report for MM Copper/Nickel Project in Southeastern Manitoba · published 24 June 2024 Ref: Table 1B. Makwa Pit Constrained and Underground Resources as of December 31, 2023
QA notes:
|
| Makwa Underground HG1 | Indicated | 0.44 Mt | — | — | 0.11% | 0.48 kt Cu | 0.83% | 3.63 kt Ni | 0.03% | 0.13 kt Co | 31 Dec 2023 | Table 1B. Makwa Pit Constrained and Underground Resources as of December 31, 2023Unverified | notes (4)Source: Grid Metals Corp. Files National Instrument 43-101 Technical Report for MM Copper/Nickel Project in Southeastern Manitoba · published 24 June 2024 Ref: Table 1B. Makwa Pit Constrained and Underground Resources as of December 31, 2023
QA notes:
|
| Makwa Underground LG1 | Indicated | 0.06 Mt | — | — | 0.08% | 0.05 kt Cu | 0.30% | 0.19 kt Ni | 0.01% | <0.01 kt Co | 31 Dec 2023 | Table 1B. Makwa Pit Constrained and Underground Resources as of December 31, 2023Unverified | notes (4)Source: Grid Metals Corp. Files National Instrument 43-101 Technical Report for MM Copper/Nickel Project in Southeastern Manitoba · published 24 June 2024 Ref: Table 1B. Makwa Pit Constrained and Underground Resources as of December 31, 2023
QA notes:
|
| Mayville Open Pit | Indicated | 32.02 Mt | 0.05 g/t | 0.05 Moz | 0.40% | 0.13 Mt Cu | 0.16% | 0.05 Mt Ni | 0.01% | 3.2 kt Co | 31 Dec 2023 | Table 1A. Mayville Pit Constrained and Underground Resource as of December 31, 2023Unverified | notes (4)Source: Grid Metals Corp. Files National Instrument 43-101 Technical Report for MM Copper/Nickel Project in Southeastern Manitoba · published 24 June 2024 Ref: Table 1A. Mayville Pit Constrained and Underground Resource as of December 31, 2023
QA notes:
|
| Mayville Underground | Indicated | 0.32 Mt | 0.11 g/t | 1.14 koz | 0.96% | 3.1 kt Cu | 0.37% | 1.19 kt Ni | 0.02% | 0.06 kt Co | 31 Dec 2023 | Table 1A. Mayville Pit Constrained and Underground Resource as of December 31, 2023Unverified | notes (4)Source: Grid Metals Corp. Files National Instrument 43-101 Technical Report for MM Copper/Nickel Project in Southeastern Manitoba · published 24 June 2024 Ref: Table 1A. Mayville Pit Constrained and Underground Resource as of December 31, 2023
QA notes:
|
| Mayville Underground | Inferred | 0.20 Mt | 0.11 g/t | 0.72 koz | 0.96% | 1.95 kt Cu | 0.32% | 0.65 kt Ni | 0.02% | 0.04 kt Co | 31 Dec 2023 | Table 1A. Mayville Pit Constrained and Underground Resource as of December 31, 2023Unverified | notes (4)Source: Grid Metals Corp. Files National Instrument 43-101 Technical Report for MM Copper/Nickel Project in Southeastern Manitoba · published 24 June 2024 Ref: Table 1A. Mayville Pit Constrained and Underground Resource as of December 31, 2023
QA notes:
|
Rows are hierarchical, not additive — do not sum a column across rows. Whole-project rows (Area “Total”) already contain the indented named-area rows beneath them, and an issuer's printed per-deposit total can itself contain other listed areas. All derived totals and rollups on this site already exclude the overlapping rows.